A supplier wins a three-year council cleaning contract at a price that works on its own staffing model. Six weeks later it discovers that forty of the outgoing contractor's cleaners are transferring across on higher hourly rates, longer holidays and a defined benefit pension. The contract makes a loss from the first month.
That is TUPE, and it catches suppliers in exactly the sectors where small companies most often bid: cleaning, security, catering, grounds maintenance, social care, transport, facilities management.
What TUPE is
The Transfer of Undertakings (Protection of Employment) Regulations 2006 protect employees when the business or service they work in changes hands. One of the situations they cover is a service provision change — when a client stops using one contractor for a service and starts using another, or brings it in-house, or contracts it out for the first time.
If the regulations apply, the employees assigned to that service transfer automatically to the new provider on the date the contract changes. They keep their existing terms and conditions, their continuity of service, and the outgoing employer's liabilities towards them transfer too.
In public sector work this happens constantly, because services are re-tendered every few years.
When it applies — and when it might not
TUPE is likely where:
- The same activities continue to be carried out for the same client.
- There is an organised grouping of employees whose main purpose is carrying out that work.
It may not apply, or apply differently, where:
- The new contract is for a single specific event or task of short duration.
- The activities are fundamentally different after the change.
- The work is wholly or mainly the supply of goods.
Whether TUPE applies is ultimately a legal question of fact, and buyers often say in the tender documents that they believe it may apply. Take that seriously, and take advice on anything significant.
What information you get
Before the transfer, the outgoing employer must give the incoming one employee liability information — identities, ages, particulars of employment, disciplinary and grievance history, claims and collective agreements — at least 28 days before the transfer.
That is far too late to price a bid. So public sector tenders usually include anonymised TUPE information from the incumbent in the tender pack: a list of roles, hours, pay rates, length of service, holiday entitlement, pension arrangements and any special terms. Public contracts typically oblige suppliers to provide this information at the end of their contract too.
Read it carefully. It is often the single most important document for your price.
What to look for in TUPE data
- Pay rates above your own. You cannot cut them simply because of the transfer.
- Holiday and sick pay above statutory minimums.
- Pensions. Staff who originally transferred out of the public sector may be entitled to keep access to a public sector pension scheme under the government's Fair Deal policy, or under the equivalent arrangements for local government. That can mean joining the Local Government Pension Scheme as an admitted body, with real employer contribution costs.
- Long service. Redundancy liability grows with it.
- Staff assigned part-time to the contract, or who work across several.
- Gaps and inconsistencies. If the data is incomplete, ask a clarification question. If the answer is still unclear, price the risk.
Pricing with TUPE
TUPE changes your price in three ways.
Labour cost. Price on the transferring staff's actual terms, not your standard ones.
Harmonisation is limited. Changing the terms of transferred employees because of the transfer is generally void, even with their agreement, except in narrow circumstances. Do not assume you can move everyone onto your contracts in year one.
Restructuring costs. If the contract needs fewer people or different roles, the cost and risk of reorganisation — consultation, potential redundancies — needs to be in the price and the timeline.
And remember TUPE works both ways. When your contract ends and someone else wins it, your staff assigned to it may transfer to them. Keep accurate records from day one.
Mobilisation and consultation
The outgoing and incoming employers both have duties to inform and consult with representatives of affected employees. In practice the incoming supplier will need to share its "measures" — any changes it plans to make that affect transferring staff — in good time.
A strong mobilisation plan in your bid should show you understand this: meetings with transferring staff, a named HR lead, payroll set-up, uniforms and induction before go-live. Evaluators of service contracts look for it.
Bid with eyes open
TUPE is not a reason to avoid public service contracts. Transferring staff know the service, the site and the client, and that is often worth more than the cost. It is a reason to read the TUPE data before you set your price, not after you win.
TendersHub shows contract details on each tender page, including contract length and what you need to bid where the notice states it, so you can spot service contracts early and request the pack in time. Search 11,100+ live UK tenders by service and area on Browse Tenders, or read how to price a public sector tender.
This post is a general guide, not legal advice. For a specific transfer, take employment law advice.