Ask a small business why it likes public sector clients and one of the first answers is: they pay. Ask why it dislikes them and one answer is often the same: eventually.
Both are true. Public bodies are under a legal duty to pay promptly, and most do. But invoices still get stuck — and knowing the rules is how you get them unstuck.
The rule
Under the Procurement Act 2023, a term is implied into public contracts that the contracting authority will pay a valid, undisputed invoice within 30 days of receiving it, or by the date the invoice says payment is due if that is later. The term cannot be overridden by anything else in the contract, although a shorter period can be agreed.
Before the Act there was an equivalent rule in the old regulations. The Act keeps it, makes it clearer, and applies it to contracts awarded under the new regime.
It reaches your subcontractors too — and you
The same 30-day term is implied into public sub-contracts: contracts in the supply chain made wholly or substantially for the purpose of delivering a public contract. If you are a subcontractor to a prime on a public contract, you are protected by the same rule. If you are the prime, you must pay your own supply chain within 30 days.
There are exceptions — concession contracts, contracts awarded by private utilities and contracts awarded by schools among them — so check what your contract is.
Buyers have to publish how they are doing
Since section 69 of the Act was brought into force, contracting authorities have to publish a payments compliance notice every six months, showing what proportion of invoices they paid within the 30-day term. The first reporting period for most authorities ran from 1 January to 31 March 2026.
That is useful information before you bid. A buyer that pays most invoices late will pay yours late too — and you can see it in advance, and price or plan your cash flow accordingly.
Why invoices get stuck
Most late public sector payments are not a refusal to pay. They are an invoice that never became valid and undisputed in the buyer's system.
The usual reasons:
- No purchase order number, or the wrong one. Many public bodies cannot pay without one.
- Sent to the wrong place. A named officer instead of the accounts payable address or e-invoicing portal the contract specifies.
- Not in the required format. Some buyers require electronic invoicing through a particular system.
- Work not "receipted". The budget holder has not confirmed in the system that the goods or service were delivered.
- A dispute nobody told you about. A query about one line holds up the whole invoice.
How to get paid on time
- Read the invoicing clause before you start work. Where invoices go, what they must include, how often you can invoice, and whether there is a portal.
- Get the PO number up front. No PO, no work, if that is how the buyer operates.
- Make the invoice impossible to reject. Contract reference, PO number, dates, a clear description that matches the contract's pricing schedule, and the correct VAT treatment.
- Confirm receipt. A short email asking accounts payable to confirm the invoice is registered can save weeks.
- Chase early, politely, and in writing. Ask whether the invoice is disputed. If it is, you need to know why. If it is not, the 30-day clock is running.
- Escalate through the contract manager. They usually want their supplier paid and can find out where it is stuck.
If it is still late
You have options:
- Statutory interest. The Late Payment of Commercial Debts (Interest) Act 1998 lets businesses claim interest on late commercial payments, unless the contract provides a substantial alternative remedy. Check your contract first.
- The buyer's complaints route. Most public bodies have a supplier payment complaints process.
- For subcontractors: if a prime on a central government contract pays you late, raise it with them first, then with the government buyer. The Cabinet Office's Public Procurement Review Service, now part of its Procurement Review Unit, takes cases about late payment of valid, undisputed invoices, including in public sector supply chains.
Use them in proportion. A relationship that lasts four years is worth protecting; but a contract you are financing interest-free is not a contract you can afford.
Plan cash flow for public work
Even when everything works, public work has a rhythm: mobilisation costs before the first invoice, monthly invoicing, 30-day terms. Build that into your cash flow before you bid, especially on a contract that is large relative to your business.
TendersHub's bid pipeline lets you track every bid from found to won, with the contract value and start date of each win, so you can see what is coming and when. Find the next one among 11,100+ live UK tenders on Browse Tenders, or see your five best matches free on /match.